<?xml version="1.0" encoding="UTF-8" standalone="no"?><ContractAwardNotice xmlns="urn:oasis:names:specification:ubl:schema:xsd:ContractAwardNotice-2" xmlns:cac="urn:oasis:names:specification:ubl:schema:xsd:CommonAggregateComponents-2" xmlns:cbc="urn:oasis:names:specification:ubl:schema:xsd:CommonBasicComponents-2" xmlns:ccts-cct="urn:un:unece:uncefact:data:specification:CoreComponentTypeSchemaModule:2" xmlns:efac="http://data.europa.eu/p27/eforms-ubl-extension-aggregate-components/1" xmlns:efbc="http://data.europa.eu/p27/eforms-ubl-extension-basic-components/1" xmlns:efext="http://data.europa.eu/p27/eforms-ubl-extensions/1" xmlns:ext="urn:oasis:names:specification:ubl:schema:xsd:CommonExtensionComponents-2" xmlns:qdt="urn:oasis:names:specification:ubl:schema:xsd:QualifiedDataTypes-2" xmlns:udt="urn:oasis:names:specification:bdndr:schema:xsd:UnqualifiedDataTypes-1"><ext:UBLExtensions><ext:UBLExtension><ext:ExtensionContent><efext:EformsExtension><efac:ContractModification><!--BT-1501(n)-Contract (Order: 01)--><efbc:ChangedNoticeIdentifier>645dd591-e914-4ab1-be04-e427b32fbede-01</efbc:ChangedNoticeIdentifier><!--BT-1501(c)-Contract (Order: 02)--><efbc:ModifiedContractIdentifier schemeName="contract">CON-0001</efbc:ModifiedContractIdentifier><efac:Change><!--BT-202-Contract (Order: 01)--><efbc:ChangeDescription languageID="DEU">AEV 03 - Die Änderung umfasst die Umsetzung des geänderten Ringdesigns für den Tübbingtunnel einschließlich der hierfür erforderlichen konstruktiven Anpassungen, statischen Nachweise sowie der planerischen Ausarbeitung der geänderten Entwurfslösung.
AEV 05 - Die Änderung umfasst die zusätzliche Auswertung der Bestandsgebäude einschließlich Ermittlung der maßgebenden Gebäudelasten sowie deren Berücksichtigung bei der statischen Bemessung der Baugrube und der Verbaukonstruktion.
AEV 13 - Die Änderung umfasst die Erstellung zusätzlicher statischer Nachweise, Verbaukonzepte und konstruktiver Detailnachweise für die Bergebaugrube. Hierzu gehören insbesondere ergänzende Nachweise für Steifen, Verbauträger, Primärstützen, Fachwerksysteme, Lastumlagerungen sowie die Fortschreibung der zugehörigen Planungsunterlagen.
AEV 14 - Die Änderung umfasst die statische und konstruktive Integration des Innenausbau-Rohbaus in den Ingenieurbau einschließlich der Bearbeitung zusätzlicher statisch relevanter Schnittstellen sowie der hieraus erforderlichen Anpassungen infolge geänderter Entwurfsvorgaben.
AEV 15 - Die Änderung umfasst die Berücksichtigung zusätzlicher Vorhaltemaße zur Einhaltung der Herstellungstoleranzen in den Bauwerken der offenen Bauweise einschließlich der hieraus erforderlichen konstruktiven Anpassungen der Bauwerks- und Schalplanung.
AEV 19 - Die Änderung umfasst die Rodung von Bäumen mit Stammdurchmessern größer 70 cm einschließlich der hierfür erforderlichen besonderen Fälltechniken, Spezialgeräte und zugehörigen Rodungsleistungen.
AEV 34 - Herstellung einer zusätzlichen rückverankerten Spundwand südlich des Danziger Platzes einschließlich Lieferung, Einbringung, Rückverankerung und zugehöriger Bauleistungen zur Herstellung des zusätzlichen Logistikgleises.
AEV 37 - Die Änderung umfasst zusätzliche statische Nachweise und konstruktive Anpassungen für den Schacht Ostendstraße einschließlich der hierfür erforderlichen Berechnungen, Nachweise und konstruktiven Bearbeitungen zur Berücksichtigung der maßgebenden Bemessungsrandbedingungen.
AEV 38 - Die Änderung umfasst die Entwicklung, statische Untersuchung und konstruktive Ausarbeitung zusätzlicher Lösungsvarianten für den Lastabtrag der Vertikallasten im Bereich des Schachtes Danziger Platz einschließlich der hierfür erforderlichen Nachweise und der Erarbeitung einer Entscheidungsgrundlage für die Festlegung der Ausführungsvariante.
AEV 39 - Die Änderung umfasst die Herstellung einer zusätzlichen rückverankerten Spundwand südlich des Danziger Platzes. Enthalten sind insbesondere Lieferung, Einbringung, Rückverankerung und zugehörige Nebenleistungen zur Sicherung des Höhenversatzes entlang des zusätzlichen Logistikgleises.
AEV 40 - Die Änderung umfasst die Berücksichtigung der Erddruckkräfte unterhalb der Baugrubensohle einschließlich der hieraus erforderlichen Anpassung des Verbausystems, der zusätzlichen Sohlaussteifung sowie aller daraus resultierenden Planungs-, Nachweis- und Bauleistungen.</efbc:ChangeDescription></efac:Change><efac:ChangeReason><!--BT-200-Contract (Order: 01)--><cbc:ReasonCode listName="modification-justification">add-wss</cbc:ReasonCode><!--BT-201-Contract (Order: 02)--><efbc:ReasonDescription languageID="DEU">AEV 03 - Zur Optimierung des Ringdesigns des Tübbingtunnels wurde eine Änderung des ursprünglichen Bauentwurfs erforderlich. Hierdurch werden zusätzliche konstruktive Anpassungen sowie statische und planerische Nachweise erforderlich, die im ursprünglichen Leistungsumfang nicht enthalten waren. Ein Auftragnehmerwechsel führt zu getrennten konstruktiven und statischen Nachweisen innerhalb desselben Ringsystems sowie zu zusätzlichen Prüf- und Bearbeitungsschritten. Hierdurch entstehen erhebliche Zusatzkosten.
AEV 05 - Für die statische Bemessung der Baugrube waren zusätzlich die Einwirkungen der zusätzlichen Bestandsbebauung zu berücksichtigen. Hierfür wurde eine ergänzende Auswertung der Bestandsgebäude einschließlich Ermittlung und Bewertung der maßgebenden Gebäudelasten erforderlich. Diese Leistungen waren im ursprünglichen Leistungsumfang nicht enthalten und stellen zusätzliche Leistungen dar. Ein Auftragnehmerwechsel führt zu getrennten Lastannahmen und statischen Nachweisen innerhalb desselben Tragwerks sowie zu zusätzlichen Prüf- und Bearbeitungsschritten. Hierdurch entstehen erhebliche Zusatzkosten.
AEV 13 - Für die Bergebaugrube wurden zusätzliche statische Nachweise, Verbaukonzepte und konstruktive Untersuchungen erforderlich, die im ursprünglichen Leistungsumfang nicht enthalten waren. Diese zusätzlichen Leistungen betreffen das statische Gesamtsystem der Bergebaugrube und müssen auf Grundlage der bereits erarbeiteten Nachweise fortgeführt werden. Ein Auftragnehmerwechsel führt zu getrennten statischen Nachweisen innerhalb desselben Tragwerks, zusätzlichen Prüf- und Integrationsleistungen sowie erheblichen Zusatzkosten.
AEV 14 - Für die statische Integration des Innenausbau-Rohbaus in den Ingenieurbau wurden zusätzliche konstruktive Bearbeitungen und statisch relevante Schnittstellen erforderlich. Darüber hinaus machten Änderungen des Entwurfs zusätzliche Anpassungen der Planung notwendig. Diese Leistungen waren im ursprünglichen Leistungsumfang nicht enthalten. Ein Auftragnehmerwechsel führt zu getrennten konstruktiven und statischen Nachweisen innerhalb desselben Tragwerks sowie zu zusätzlichen Prüf- und Bearbeitungsschritten. Hierdurch entstehen erhebliche Zusatzkosten.
AEV 15 - Nachträglich wurde festgelegt, dass bei den Bauwerken der offenen Bauweise zusätzliche Vorhaltemaße zur Berücksichtigung der Herstellungstoleranzen einzuhalten sind. Hierdurch werden konstruktive Anpassungen der Bauwerksgeometrie sowie der betroffenen Bauwerksdetails erforderlich, die im ursprünglichen Leistungsumfang nicht enthalten waren. Eine getrennte Bearbeitung dieser Anpassungen führt zu zusätzlichen konstruktiven Schnittstellen, wiederholten Prüf- und Bearbeitungsschritten sowie erheblichen Zusatzkosten. 
AEV 19 - Im Zuge der Baufeldfreimachung wurden Rodungsarbeiten an Bäumen mit Stammdurchmessern größer 70 cm erforderlich. Derartige Baumdurchmesser sind im Hauptleistungsverzeichnis nicht enthalten und stellen zusätzliche Leistungen dar. Die Durchführung dieser Rodungsarbeiten erfordert besondere Fälltechniken sowie den Einsatz spezieller Geräte. Ein Auftragnehmerwechsel führt zu zusätzlichem Aufwand bei der Durchführung der Rodungsarbeiten sowie zu erheblichen Zusatzkosten infolge erneut erforderlicher Geräte- und Baustelleneinrichtungen.
AEV 34 - Die Herstellung der zusätzlichen Spundwand wurde im Zusammenhang mit der nachträglichen Planung eines zusätzlichen Logistikgleises erforderlich. Die hierfür erforderlichen Ausführungsleistungen waren nicht Bestandteil des ursprünglichen Vertragsumfangs und stellen zusätzliche Leistungen zur Herstellung des Logistikgleises dar.
AEV 37 - Für den Schacht Ostendstraße wurden zusätzliche statische Nachweise und konstruktive Anpassungen zur Berücksichtigung der Einwirkungen aus den maßgebenden Randbedingungen erforderlich. Diese Leistungen waren im ursprünglichen Leistungsumfang nicht enthalten und stellen zusätzliche Leistungen dar. Ein Auftragnehmerwechsel führt zu getrennten statischen und konstruktiven Nachweisen innerhalb derselben Tragkonstruktion sowie zu zusätzlichen Prüf- und Bearbeitungsschritten. Hierdurch entstehen erhebliche Zusatzkosten.
AEV 38 - Für den Lastabtrag der Vertikallasten im Bereich des Schachtes Danziger Platz enthält die Entwurfsplanung keine Ausführungsvariante. Zur Festlegung der Ausführungsvariante wurde die Entwicklung und Bewertung zusätzlicher konstruktiver Lösungsvarianten erforderlich. Diese Leistungen waren im ursprünglichen Leistungsumfang nicht enthalten. Ein Auftragnehmerwechsel führt zu getrennten statischen und konstruktiven Nachweisen innerhalb derselben Tragkonstruktion sowie zu zusätzlichem Aufwand bei der Integration der ausgewählten Variante in die weitere Planung und Ausführung. Hierdurch entstehen erhebliche Zusatzkosten.
AEV 39 - Die Herstellung der zusätzlichen Spundwand wurde im Zusammenhang mit der nachträglichen Planung eines zusätzlichen Logistikgleises erforderlich. Die Spundwand ist unmittelbar in die Herstellung des Logistikgleises sowie die hierfür erforderlichen Bauzustände eingebunden und kann technisch nicht losgelöst ausgeführt werden. Ein Auftragnehmerwechsel erfordert eine erneute technische Abstimmung der konstruktiven Lösung sowie der statischen und geotechnischen Nachweise und führt zu Verzögerungen im Bauablauf. Hierdurch entstehen erhebliche Zusatzkosten infolge von Behinderungen, erforderlichen Anpassungen der Bauabläufe sowie nachgelagerten Terminverschiebungen.
AEV 40 - Die Berücksichtigung der Erddruckkräfte unterhalb der Baugrubensohle macht eine Änderung des Bauentwurfs der Stationsbaugrube erforderlich. Hierdurch werden zusätzliche Aussteifungselemente sowie weitere Anpassungen des statischen Gesamtsystems erforderlich, die im ursprünglichen Leistungsumfang nicht enthalten waren. Ein Auftragnehmerwechsel führt zu getrennten statischen Nachweisen innerhalb derselben Tragkonstruktion sowie zu zusätzlichen Prüf- und Ausführungsleistungen. Hierdurch entstehen erhebliche Zusatzkosten</efbc:ReasonDescription></efac:ChangeReason></efac:ContractModification><efac:NoticeResult><!--BT-161-NoticeResult (Order: 02)--><cbc:TotalAmount currencyID="EUR">0</cbc:TotalAmount><efac:LotResult><!--OPT-322-LotResult (Order: 02)--><cbc:ID>RES-0001</cbc:ID><efac:LotTender><!--OPT-320-LotResult (Order: 02)--><cbc:ID schemeName="tender">TEN-0001</cbc:ID></efac:LotTender><efac:SettledContract><!--OPT-315-LotResult (Order: 01)--><cbc:ID schemeName="contract">CON-0001</cbc:ID></efac:SettledContract><efac:TenderLot><!--BT-13713-LotResult (Order: 01)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID></efac:TenderLot></efac:LotResult><efac:LotTender><!--OPT-321-Tender (Order: 02)--><cbc:ID>TEN-0001</cbc:ID><cac:LegalMonetaryTotal><!--BT-720-Tender (Order: 10)--><cbc:PayableAmount currencyID="EUR">0</cbc:PayableAmount></cac:LegalMonetaryTotal><efac:SubcontractingTerm><!--BT-773-Tender (Order: 05)--><efbc:TermCode listName="applicability">not-known</efbc:TermCode></efac:SubcontractingTerm><efac:TenderingParty><!--OPT-310-Tender (Order: 01)--><cbc:ID schemeName="tendering-party">TPA-0001</cbc:ID></efac:TenderingParty><efac:TenderLot><!--BT-13714-Tender (Order: 01)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID></efac:TenderLot><efac:TenderReference><!--BT-3201-Tender (Order: 01)--><cbc:ID>20251043082-0</cbc:ID></efac:TenderReference></efac:LotTender><efac:SettledContract><!--OPT-316-Contract (Order: 01)--><cbc:ID>CON-0001</cbc:ID><!--BT-1451-Contract (Order: 02)--><cbc:AwardDate>2025-04-24+02:00</cbc:AwardDate><!--BT-145-Contract (Order: 03)--><cbc:IssueDate>2025-05-05+02:00</cbc:IssueDate><efac:ContractReference><!--BT-150-Contract (Order: 01)--><cbc:ID>CON-0001 - Implenia Civil Engineering GmbH</cbc:ID></efac:ContractReference><efac:LotTender><!--BT-3202-Contract (Order: 02)--><cbc:ID schemeName="tender">TEN-0001</cbc:ID></efac:LotTender></efac:SettledContract><efac:TenderingParty><!--OPT-210-Tenderer (Order: 01)--><cbc:ID>TPA-0001</cbc:ID><efac:Tenderer><!--OPT-300-Tenderer (Order: 01)--><cbc:ID schemeName="organization">ORG-0003</cbc:ID></efac:Tenderer></efac:TenderingParty></efac:NoticeResult><efac:NoticeSubType><!--OPP-070-notice (Order: 01)--><cbc:SubTypeCode listName="notice-subtype">39</cbc:SubTypeCode></efac:NoticeSubType><efac:Organizations><efac:Organization><efac:Company><!--BT-505-Organization-Company (Order: 01)--><cbc:WebsiteURI>https://www.deutschebahn.com/bieterportal</cbc:WebsiteURI><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0001</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">DB Netz AG (Bukr 16)</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Adam-Riese-Straße 11-13</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Frankfurt Main</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>60327</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE712</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>f45ee0d3-f9b6-44f0-846d-0c10b6f61a37</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-502-Organization-Company (Order: 03)--><cbc:Name>FE.EI-M-B</cbc:Name><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49 6926523916</cbc:Telephone><!--BT-739-Organization-Company (Order: 07)--><cbc:Telefax>+49 06926520071</cbc:Telefax><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>josip.peraica@deutschebahn.com</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0002</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">Vergabekammer des Bundes</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Kaiser-Friedrich-Straße 16</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Bonn</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>53113</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DEA22</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>0a9ea480-08e4-4ab6-bf12-d722d0ad54b6</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49 22894990</cbc:Telephone><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>vk@bundeskartellamt.bund.de</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0003</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">Implenia Civil Engineering GmbH</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Am Prime-Parc 1</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Raunheim</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>65479</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE717</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>5f0127dc-47d2-4e66-93cd-3a27c6b67caa</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49</cbc:Telephone><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>bieterportal-alt@deutschebahn.com</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><cbc:ID schemeName="organization">ORG-0004</cbc:ID></cac:PartyIdentification><cac:PartyName><cbc:Name languageID="DEU">Datenservice Öffentlicher Einkauf (in Verantwortung des Beschaffungsamts des BMI)</cbc:Name></cac:PartyName><cac:PostalAddress><cbc:CityName>Bonn</cbc:CityName><cbc:PostalZone>53119</cbc:PostalZone><cbc:CountrySubentityCode listName="nuts">DEA22</cbc:CountrySubentityCode><cac:Country><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><cbc:CompanyID schemeID="002">0204:994-DOEVD-83</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><cbc:Telephone>+49228996100</cbc:Telephone><cbc:ElectronicMail>noreply.esender_hub@bescha.bund.de</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization></efac:Organizations><efac:Publication><efbc:NoticePublicationID schemeName="ojs-notice-id">00546635-2026</efbc:NoticePublicationID><efbc:GazetteID schemeName="ojs-id">150/2026</efbc:GazetteID><efbc:PublicationDate>2026-08-06+02:00</efbc:PublicationDate></efac:Publication></efext:EformsExtension></ext:ExtensionContent></ext:UBLExtension></ext:UBLExtensions><!--OPT-001-notice (Order: 02)--><cbc:UBLVersionID>2.3</cbc:UBLVersionID><!--OPT-002-notice (Order: 03)--><cbc:CustomizationID>eforms-sdk-1.13</cbc:CustomizationID><!--BT-701-notice (Order: 06)--><cbc:ID schemeName="notice-id">bdc9763d-b302-4541-88f1-0d191d7061aa</cbc:ID><!--BT-04-notice (Order: 09)--><cbc:ContractFolderID>5693c395-219a-4ee6-a48e-768f698fc807</cbc:ContractFolderID><!--BT-05(a)-notice (Order: 10)--><cbc:IssueDate>2026-08-05+02:00</cbc:IssueDate><!--BT-05(b)-notice (Order: 11)--><cbc:IssueTime>09:28:24+02:00</cbc:IssueTime><!--BT-757-notice (Order: 13)--><cbc:VersionID>01</cbc:VersionID><!--BT-738-notice (Order: 16)--><cbc:RequestedPublicationDate>2026-08-05+02:00</cbc:RequestedPublicationDate><!--BT-01-notice (Order: 18)--><cbc:RegulatoryDomain>32014L0025</cbc:RegulatoryDomain><!--BT-02-notice (Order: 19)--><cbc:NoticeTypeCode listName="cont-modif">can-modif</cbc:NoticeTypeCode><!--BT-702(a)-notice (Order: 21)--><cbc:NoticeLanguageCode>DEU</cbc:NoticeLanguageCode><cac:ContractingParty><cac:Party><cac:PartyIdentification><!--OPT-300-Procedure-Buyer (Order: 02)--><cbc:ID schemeName="organization">ORG-0001</cbc:ID></cac:PartyIdentification><cac:ServiceProviderParty><cbc:ServiceTypeCode listName="organisation-role">ted-esen</cbc:ServiceTypeCode><cac:Party><cac:PartyIdentification><cbc:ID schemeName="organization">ORG-0004</cbc:ID></cac:PartyIdentification></cac:Party></cac:ServiceProviderParty></cac:Party></cac:ContractingParty><cac:TenderingTerms><cac:ProcurementLegislationDocumentReference><cbc:ID>sektvo</cbc:ID><cbc:DocumentDescription languageID="DEU">Der Wert des Ergebnisses (Feld-ID: BT-720-Tender) wird gemäß § 38 Abs. 6 SektVO nicht veröffentlicht, da hiervon ​Betriebs- und Geschäftsgeheimnisse des Auftragnehmers betroffen wären und die Offenlegung dieser Angabe dessen ​berechtigten geschäftlichen Interessen schädigen würde. Zudem würde die Angabe den lauteren Wettbewerb zwischen ​Wirtschaftsteilnehmern beeinträchtigen.</cbc:DocumentDescription></cac:ProcurementLegislationDocumentReference></cac:TenderingTerms><cac:ProcurementProject><!--BT-22-Procedure (Order: 02)--><cbc:ID>22FEI62593</cbc:ID><!--BT-21-Procedure (Order: 03)--><cbc:Name languageID="DEU">SPGK_Nordmainische S-Bahn - VP1, Rohbau Tunnel und unterirdische Verkehrsstation</cbc:Name><!--BT-24-Procedure (Order: 04)--><cbc:Description languageID="DEU">BE-Fläche 47.000m², Aushub/Verfüllung Station 239.400 m³, Aushub/Verfüllung Trog 22.600 m³, Aushub/Verfüllung Schächte 48.000 m³, Verfüllung Station inkl. Verfüllung Bohrugen 17.500 m³, Verfüllung Trog inkl. Verfüllung Bohrungen 2.500 m³, Verfüllung Schächte/Tunnel inkl. Verfüllung Borhungen 25.000 m³,  Tunnelröhre für Fahrbahn Nordröhre (ohne unterirdische Verkehrsstation) 1.200 m, Tunnelröhre für Fahrbahn Südröhre (ohne unterirdische Verkehrsstation) 1.200 m, Trog (für beide Fahrbahnen) 187 m, Länge Verkehrsstation inkl. jeweils 2m Dicke Wände 214 m, Beton Verkehrsstation inkl. Beton für Bohrpfähle und Magerbeton 91.000 m³, Beton Tunnel + VGF 56.500 m³, Beton Trog 8.800 m³, Stahl Verkehrsstation, Bewehrungsstahl, ohne Stahlbeton! -&gt; siehe Beton 10.100 to, Stahl Tunnel Bewehrungsstahl  6.000 to, Stahl Trog Bewehrungsstahl 1.100 to, Bohrpfähle Station 19.900 m, Bohrpfähle Trog 4.400 m, Bohrpfähle  Tunnel/Schächte 20.100 m, Spundwand/Verbau Trägerbohlverbau Station 2.100 m², Spundwand/Verbau Trog 900 m², Spundwand/Verbau Tunnel/Schächte 2.800 m², 1 St. Tunnelvortriebsmaschine, Wasserschutzmaßnahmen Einleitung in den Main Station 8.900.000 m³, Wasserschutzmaßnahmen Einleitung in den Main Trog 6.400 m³, Wasserschutzmaßnahmen Einleitung in den Main / Kanalisation Tunnel/Schächte 1.900.000 m³
</cbc:Description><!--BT-23-Procedure (Order: 05)--><cbc:ProcurementTypeCode listName="contract-nature">works</cbc:ProcurementTypeCode><cac:MainCommodityClassification><!--BT-262-Procedure (Order: 05)--><cbc:ItemClassificationCode listName="cpv">45221247</cbc:ItemClassificationCode></cac:MainCommodityClassification><cac:RealizedLocation><cac:Address><!--BT-5131-Procedure (Order: 20)--><cbc:CityName>Frankfurt am Main</cbc:CityName><!--BT-5121-Procedure (Order: 21)--><cbc:PostalZone>60314</cbc:PostalZone><!--BT-5071-Procedure (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE712</cbc:CountrySubentityCode><cac:Country><!--BT-5141-Procedure (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:Address></cac:RealizedLocation></cac:ProcurementProject><cac:ProcurementProjectLot><!--BT-137-Lot (Order: 02)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID><cac:TenderingTerms><ext:UBLExtensions><ext:UBLExtension><ext:ExtensionContent><efext:EformsExtension><efac:StrategicProcurement><!--BT-717-Lot (Order: 01)--><efbc:ApplicableLegalBasis listName="cvd-scope">false</efbc:ApplicableLegalBasis></efac:StrategicProcurement></efext:EformsExtension></ext:ExtensionContent></ext:UBLExtension></ext:UBLExtensions><!--BT-94-Lot (Order: 18)--><cbc:RecurringProcurementIndicator>false</cbc:RecurringProcurementIndicator><cac:PaymentTerms><!--BT-77-Lot (Order: 05)--><cbc:Note languageID="DEU">Die Zahlungsbedingungen gelten gemäß Vergabeunterlagen.</cbc:Note></cac:PaymentTerms><cac:TendererQualificationRequest><!--BT-761-Lot (Order: 02)--><cbc:CompanyLegalFormCode listName="required">false</cbc:CompanyLegalFormCode></cac:TendererQualificationRequest><cac:ContractExecutionRequirement><!--BT-736-Lot (Order: 03)--><cbc:ExecutionRequirementCode listName="reserved-execution">no</cbc:ExecutionRequirementCode></cac:ContractExecutionRequirement><cac:ContractExecutionRequirement><!--OPT-060-Lot (Order: )--><cbc:ExecutionRequirementCode listName="conditions">performance</cbc:ExecutionRequirementCode><!--BT-70-Lot (Order: 04)--><cbc:Description languageID="DEU">Entfällt</cbc:Description></cac:ContractExecutionRequirement><cac:ContractExecutionRequirement><!--BT-743-Lot (Order: 03)--><cbc:ExecutionRequirementCode listName="einvoicing">required</cbc:ExecutionRequirementCode></cac:ContractExecutionRequirement><cac:AdditionalInformationParty><cac:PartyIdentification><!--OPT-301-Lot-AddInfo (Order: 02)--><cbc:ID schemeName="organization">ORG-0001</cbc:ID></cac:PartyIdentification></cac:AdditionalInformationParty><cac:AppealTerms><cac:PresentationPeriod><!--BT-99-Lot (Order: 08)--><cbc:Description languageID="DEU">Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.</cbc:Description></cac:PresentationPeriod><cac:AppealInformationParty><cac:PartyIdentification><!--OPT-301-Lot-ReviewInfo (Order: 02)--><cbc:ID schemeName="organization">ORG-0002</cbc:ID></cac:PartyIdentification></cac:AppealInformationParty><cac:AppealReceiverParty><cac:PartyIdentification><!--OPT-301-Lot-ReviewOrg (Order: 02)--><cbc:ID schemeName="organization">ORG-0002</cbc:ID></cac:PartyIdentification></cac:AppealReceiverParty></cac:AppealTerms><cac:PostAwardProcess><!--BT-92-Lot (Order: 04)--><cbc:ElectronicOrderUsageIndicator>true</cbc:ElectronicOrderUsageIndicator><!--BT-93-Lot (Order: 05)--><cbc:ElectronicPaymentUsageIndicator>true</cbc:ElectronicPaymentUsageIndicator></cac:PostAwardProcess></cac:TenderingTerms><cac:TenderingProcess><!--BT-115-Lot (Order: 13)--><cbc:GovernmentAgreementConstraintIndicator>true</cbc:GovernmentAgreementConstraintIndicator><cac:ContractingSystem><!--BT-765-Lot (Order: 03)--><cbc:ContractingSystemTypeCode listName="framework-agreement">none</cbc:ContractingSystemTypeCode></cac:ContractingSystem></cac:TenderingProcess><cac:ProcurementProject><!--BT-22-Lot (Order: 02)--><cbc:ID>7d83f2b8-3001-4b5f-b7c9-f8c7ad2ae6f4</cbc:ID><!--BT-21-Lot (Order: 03)--><cbc:Name languageID="DEU">SPGK_Nordmainische S-Bahn - VP1, Rohbau Tunnel und unterirdische Verkehrsstation</cbc:Name><!--BT-24-Lot (Order: 04)--><cbc:Description languageID="DEU">BE-Fläche 47.000m², Aushub/Verfüllung Station 239.400 m³, Aushub/Verfüllung Trog 22.600 m³, Aushub/Verfüllung Schächte 48.000 m³, Verfüllung Station inkl. Verfüllung Bohrugen 17.500 m³, Verfüllung Trog inkl. Verfüllung Bohrungen 2.500 m³, Verfüllung Schächte/Tunnel inkl. Verfüllung Borhungen 25.000 m³,  Tunnelröhre für Fahrbahn Nordröhre (ohne unterirdische Verkehrsstation) 1.200 m, Tunnelröhre für Fahrbahn Südröhre (ohne unterirdische Verkehrsstation) 1.200 m, Trog (für beide Fahrbahnen) 187 m, Länge Verkehrsstation inkl. jeweils 2m Dicke Wände 214 m, Beton Verkehrsstation inkl. Beton für Bohrpfähle und Magerbeton 91.000 m³, Beton Tunnel + VGF 56.500 m³, Beton Trog 8.800 m³, Stahl Verkehrsstation, Bewehrungsstahl, ohne Stahlbeton! -&gt; siehe Beton 10.100 to, Stahl Tunnel Bewehrungsstahl  6.000 to, Stahl Trog Bewehrungsstahl 1.100 to, Bohrpfähle Station 19.900 m, Bohrpfähle Trog 4.400 m, Bohrpfähle  Tunnel/Schächte 20.100 m, Spundwand/Verbau Trägerbohlverbau Station 2.100 m², Spundwand/Verbau Trog 900 m², Spundwand/Verbau Tunnel/Schächte 2.800 m², 1 St. Tunnelvortriebsmaschine, Wasserschutzmaßnahmen Einleitung in den Main Station 8.900.000 m³, Wasserschutzmaßnahmen Einleitung in den Main Trog 6.400 m³, Wasserschutzmaßnahmen Einleitung in den Main / Kanalisation Tunnel/Schächte 1.900.000 m³
</cbc:Description><!--BT-23-Lot (Order: 05)--><cbc:ProcurementTypeCode listName="contract-nature">works</cbc:ProcurementTypeCode><cac:ProcurementAdditionalType><!--BT-06-Lot (Order: 02)--><cbc:ProcurementTypeCode listName="strategic-procurement">none</cbc:ProcurementTypeCode></cac:ProcurementAdditionalType><cac:MainCommodityClassification><!--BT-262-Lot (Order: 05)--><cbc:ItemClassificationCode listName="cpv">45221247</cbc:ItemClassificationCode></cac:MainCommodityClassification><cac:RealizedLocation><cac:Address><!--BT-5131-Lot (Order: 20)--><cbc:CityName>Frankfurt am Main</cbc:CityName><!--BT-5121-Lot (Order: 21)--><cbc:PostalZone>60314</cbc:PostalZone><!--BT-5071-Lot (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE712</cbc:CountrySubentityCode><cac:Country><!--BT-5141-Lot (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:Address></cac:RealizedLocation><cac:PlannedPeriod><!--BT-536-Lot (Order: 02)--><cbc:StartDate>2025-05-26+02:00</cbc:StartDate><!--BT-537-Lot (Order: 04)--><cbc:EndDate>2033-02-01+01:00</cbc:EndDate></cac:PlannedPeriod></cac:ProcurementProject></cac:ProcurementProjectLot><cac:TenderResult><!--OPT-999 (Order: 06)--><cbc:AwardDate>2025-05-05+02:00</cbc:AwardDate></cac:TenderResult></ContractAwardNotice>